The Councillor for Agriculture and districts, Francisco Martínez Escandell, last week visited the works that are being developed in some rural roads of the municipality for which has increased the staff of municipal workers, with four operators over who, during the coming months, will be performing several works adequacy and bumpy in various parts of town.
As explained Escandell Francisco Martínez, "the vastness of the town of Jumilla poses to the City a great economic effort in regard to investments repair and maintenance of roads, which is shaping itself in their budgets annually, and currently has its own park construction equipment. "
For this reason, and as reinforcement of staff that the City account for these jobs, the Department has strengthened the template with more than four workers are developing different jobs in 32 bumpy roads of the town.
Some of the roads on which they act will be the head of Colonization in the sections 1.2 and 3, Alicante Road, Tower Road to the Houses of Poveda, Camino de las Casas Poveda to Zarza, road Raja, the Romerales, or Salt de la Rosa, among others.
The work to be performed consistent in repairing potholes is first made, in the preparation of the land on which it will perform, followed by sanitation and patching it.
Subsequently compacted 'and could add' the tack coat.
Finally apply 'the wearing course of asphalt to let suitable for local traffic.
Besides the operations necessary for the clearance, clearing and cleaning margins in areas where visibility is poor and hinder the transit will take place.
Source: Ayuntamiento de Jumilla