Are already doing the work necessary to build a deck in the bleachers of the football field, located in the Polideportivo Municipal 'La Hoya' of Jumilla.
In this way the fans will have this protection before the end of the year.
This is another project being developed with funding from the Investment Plan of the Government of Spain, Plan E 2011.
As confirmed by the Mayor of Jumilla Francisco Abellán, "one of the requirements is that the works are completed before year end."
Abellán added that "these steps will improve the image of the field and also the comfort of the fans, hopefully that enhances the fan support to the field, especially in winter, and all the Jumilla CF accompany this new season .
The project was written by David Boixader Cambronero Industrial Engineer and the contractor is Saico, SA Intagua Construction and Services.
The award amount of 91,197.72 euros has been more than 14,591.64 euros in VAT.
Reflected in the draft to be held to build a light deck sandwich panel 55 x 8.0 m floor dimensions.
The cover is supported by metal straps would outline in cold.
The main structure was solved by a cantilever with metal hot rolled variable section of 8.00 m span (to face of column) and columns of constant section.
To do so, according to the project, has hired three employees.
Source: Ayuntamiento de Jumilla