It has already completed the electrification of the farm from which will benefit 14 users (15/07/2010)

Have already completed the work of rural electrification of the farm from which will benefit a total of 14 users, as confirmed by Jesus Sanchez, a councilor of Industry and Economics.

Sanchez said that "action has been important for the number of beneficiaries, of which several of them are agricultural and livestock store."

As for the work performed, was carried out air-ground line of high tension, a length of 1,344 meters of which 1,279 are air and 65 underground, at a voltage of 20kv.

It has also built a processing plant, a power of 100 kVA and has run a low voltage overhead line with a length of 1,123 meters at a voltage 230/400v.

From this is where users will have their connections with Iberdrola.

This action has had a total cost of 67,518 euros, of which it has received a grant from the region of 24,268 euros (36%) and the remaining 43,250 euros (64%) is contributed by the beneficiaries themselves.

Source: Ayuntamiento de Jumilla

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
Este sitio web utiliza cookies para facilitar y mejorar la navegación. Si continúas navegando, consideramos que aceptas su uso. Más información