Reconstruction works are underway on the wall of the Antonio Ibáñez football field, which was knocked down by a windstorm.
They are being carried out by the winning company Ayllonza, at a cost of 40,246.64 euros.Since it is the enclosure of the Municipal Sports Center, it is being built in the place of the previous one and with the same characteristics, that is, based on precast concrete panels of 2.50 m.
high and 5.00 m.
in length, between rolled steel profiles.On the west side, the existing wall has been dismantled to create a foundation based on isolated footings to later reassemble the wall reusing the same steel profiles and concrete panels that form it.
Source: Ayuntamiento de Jumilla