The Mayor of Jumilla states that "The works that are running in Plan E are at a good pace" (29/06/2009)

Recently, the Mayor and Councillor of Public Works and Urbanism Francisco Abellán, accompanied by Councilman Antonio Martínez and Technical Services Works Department has made a visit to some of the works being implemented within the National Investment Plan that ended in Local Zapatero's government up and Jumilla which have invested more than 4 million euros.

Likewise, visited other actions currently being developed in Jumilla, as the Multipurpose building for groups and associations and works that are underway in Goya street.

As for the works of Plan E, Francisco Abellán has stated that "after the decision of the administrative procedures necessary, we have had the opportunity to check that all jobs go at a good pace and that possibly be fulfilled on schedule, although some cases have to request an extension of dates. "

The mayor added that "all these measures, in addition to being a development of the city in various aspects, is also creating economic movement and firm-level recruitment of unemployed workers."

The projects concern the running of the highway from Santa Ana, implementation and upgrading of access road to the castle and its surroundings, the suitability of the two roundabouts on the Way of the French, the expansion of the Botanical Garden located at the hamlet of La Estacada, civil works for industrial buildings for the promotion and business development with the construction of four industrial buildings on a municipal plot of Polygon The Romerales, construction of an Animal Shelter and rehabilitation of Municipal House of Culture.

Regarding the construction of the Multipurpose Building for groups and associations, Abellán has also expressed his satisfaction with the result being obtained, "Work is also going very well and is well worth being a building to house numerous associations Jumilla ".

This building had a budget allocation of nearly 2,000,000 euros.

This work is being carried out by Ferrovial Agroman SA Comprehensive Center for Multiple Groups of Jumilla is being built on a plot of land dotacional groups, owned by the municipality and located at the confluence of the street Juan XXIII and doctor Juan Martinez, next to the current Court .

Will have four floors, plus basement and attic floor comprising a total floor area of 2410.82 meters square.

Will feature meeting rooms, offices, auditorium and cafeteria.

Finally, the technical authorities and visited some construction work taking place in Goya street in the Works and Services Plan (POS) 2009.

It is the packaging of a paved stretch of Goya street between the street Antonio Mañas and the Way of the French.

Source: Ayuntamiento de Jumilla

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
Este sitio web utiliza cookies para facilitar y mejorar la navegación. Si continúas navegando, consideramos que aceptas su uso. Más información